Goal
Enhance LGs ability to plan and manage financial resources for effective and sustainable delivery of services
Objectives
  • IFMS installed and operationalised in LGs
  • Capacity of LGs to deliver services enhances
  • Capacity of local communities to engage in productive activities strengthened

Performance in FY 2011/12

i) 63 classrooms and teachers’ houses were constructed;

ii) 41 health projects were undertaken;

iii) 32 latrines were constructed as part of a wider effort to boost sanitation levels;

iv) Investment works on 89 administration blocks in Northern Uganda were

undertaken;

v) Construction works in 12 markets were undertaken;

vi) 53 roads and drainage projects were undertaken;

vii) 64 water supply projects were undertaken;

viii) 37 heifer, piggery and apiary projects were undertaken across the country;

ix) 6 LGs were piloted under the Integrated Financial Management System (IFMS) Tier 2;

x) IFMS Tier 1 was implemented in 8 LGs namely; Bushenyi, Jinja, Lira, Masaka, Mbale, Mpigi, Mbarara and Soroti.